Cuttack - Angul Section Four Laning Project, NH-42, Odisha
国家和地区:
India
项目名称:
Cuttack - Angul Section Four Laning Project, NH-42, Odisha
领域:
Highway/Motorway
项目类型:
Upgrade/Maintenance
项目性质:
Public
项目经费 (USD Millions):
283
规模:
112
规模单位:
km
参加单位:
National Highways Authority of India (NHAI)[Sponsor]{India},Gayatri Projects[Construction]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2021
项目说明:
April 2021 - Construction underway; October 2020 - 40% of work has been completed on the entire stretch between Sambalpur, Angul and Cuttack; December 2018 - Foundation stone laid; January 2018 - Gayatri Projects Ltd appointed as EPC contractor for both packages; September 2015 - Cabinet Committee on Economic Affairs approved the project; Project will be implemented in 2 packages, Package I includes the construction of a highway from 0.400km to 60.200km and Package II includes the construction of a highway from 60.200km to 112km; Project cost - INR19.9bn