Asian Development Bank (ADB)[Financier]{Philippines},Bangladesh Roads and Highways Department (RHD)[Sponsor]{Bangladesh},China Harbour Engineering Company (CHEC)[Construction]{China}
项目状态:
At planning stage
开始时间:
-
结束时间:
2026
项目说明:
September 2021 - Land acquisition underway; January 2020 - Government decided to fund the work by themselves after blacklisting the CHEC for bribery; January 2018 - Government blacklisted the construction company that was going to work on this project; June 2017 - CHEC is demanding additional BDT7.5bn (USD92mn) to carry out the project; May 2017 - CHEC is going to withdraw itself from the project, as it did not agree to the proposal of the Bangladesh government; October 2016 - CHEC appointed to construct the road under a G-to-G arrangement; Project is a part of Dhaka-Sylhet-Tamabil Highway Four Laning Project; Project cost - BDT200bn; [B&R]