National Highways & Infrastructure Development (NHIDCL)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
February 2021 - Construction underway on the project; July 2018 - Work commenced on Dimapur bypass with Joint venture of Gawar Constructions and Singh Construction; Project includes construction from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion on EPC basis; Project cost - INR5bn