December 2021 - Construction underway; September 2021 - Project will take on average 42 months to complete; June 2021 - Contract has been awarded to Raubex for the construction; October 2019 - Sanral to issue tender for N2 and N3 freeway projects; November 2015 - Design work started after WSP won tender; Project includes upgrades from Dardanelles Interchange (km 26.6) to Lynnfield Park Interchange (km 30.6); Project is part of 80 km N3 National Road Upgrade; Project cost - ZAR1.48bn