Japan International Cooperation Agency (JICA)[Financier]{Japan},Paraguay Public Works and Communications Ministry (MOPC)[Sponsor]{Paraguay},Benito Roggio[Construction]{Argentina}
项目状态:
Under construction
开始时间:
2018
结束时间:
2021
项目说明:
August 2021 - Construction completed 93%; April 2018 - Construction started; December 2017 - Contracts awarded for the three tranches of the project; April 2017 - JICA provided a loan of USD162mn; Project will run parallel to the Parana river from the town of Natalio in southern Paraguay Itapua department to Cedrales in Alto Parana; Project is a part of Export Corridor, Natalio (Itapua) - Cedrales (Alto Parana); Project cost - PYG303.88bn (USD46mn)