Texas Department of Transportation (TxDOT)[Sponsor]{United States},Zachry Construction[Construction]{United States}
项目状态:
Under construction
开始时间:
2017
结束时间:
2021
项目说明:
June 2021 - Project nearing completion; June 2020 - All westbound I-20 traffic to left (south) has been shifted onto newly reconstructed section of interstate to allow work to begin on northern side of I-20; November 2019 - Project has been delayed due to weather and other issues and its completion has been pushed from 2020 to 2021; Total length - 3mile