TK Engineering group[Construction]{India},ARSS Infrastructure[Construction]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2017
结束时间:
-
项目说明:
August 2021 - Work on Package B and C will start soon; April 2021 - Ministry of Road Transport and Highways (MoRTH) of India has approved the construction of four highway projects with a combined length of 52.4km; December 2020 - ARSS Infra has been awarded a contract worth INR3.01bn (USD40.7mn) for Package C; November 2020 - Package A is under construction; June 2020 - Ministry of road, transport and highways (MoRTH) has given the financial sanction as well as administrative and technical approval for both Packages B and C; April 2020 - State government has urged the Centre to clear the pending Packages B and C of the Itanagar-Banderdewa highway project; October 2016 - Project got approval from Central Government