Government of Australia[Sponsor]{Australia},Queensland Government[Sponsor]{Australia},Vinci Construction[Construction]{France},Seymour Whyte Constructions[Construction]{Australia}
项目状态:
Under construction
开始时间:
2020
结束时间:
2023
项目说明:
October 2021 - Construction underway; June 2020 - Vinci won AUD97mn (USD67mn) contract to widen a 2 km section; May 2020 - Construction begins and will be delivered in three stages while Varsity Lakes-Burleigh section to be delivered first; April 2020 - Seymour Whyte Constructions won contract to deliver the Package A; Project is jointly funded by the Australian Government AUD500mn (USD320mn) and Queensland Government contributing AUD500mn (USD320mn) each; Project cost - AUD1bn