September 2020 - Project completed; September 2018 - Kier to go ahead with project alone following Carillion liquidation; September 2017 - Plans for the project have been unveiled; July 2015 - Carillion and Kier Group JV has been awarded contract for project; Construction work began in September 2018; Project length - 11 miles; Project cost - GBP164mn