National Highways Authority of India (NHAI)[Sponsor]{India},Government of India[Sponsor]{India}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
July 2021 - Land acquisition underway; December 2020 - Construction work planned to commence in 2021 and will take 30 months to complete; Project comprises 4 packages, Package I (89 km) from Palia to Shahajahanpur Bypass, Package II (85.641 km) from Shahajahanpur Bypass to Hardoi Bypass, Package III (54.429 km) from Hardoi Bypass to end of Hardoi district and Package IV (36.944 km) from end of Hardoi district to Lucknow (Dubagga Chauraha); Project cost - INR40bn