Chilean Ministry of Public Works[Sponsor]{Chile},Obrascon Huarte Lain (OHL)[Operator]{Spain}
项目状态:
At planning stage
开始时间:
-
结束时间:
2022
项目说明:
January 2022 - Concessions Technical Panel (PTC) decided to rule in favor of the company in charge of the works; August 2021 - Residents of the Maitencillo-Puchuncavi community continue to oppose the project; May 2020 - Project is in the list of regional investment project 2021; March 2020 - In January 2020, the installation of work began by the Canopsa for the collection of materials, machinery, and the installation of containers for the work crews; April 2018 - Public consultation underway for project; September 2016 - Contract awarded to OHL Group for project; December 2015 - Tender launched; Project involves upgrade of 27 km route and development of 16 km bypass to Laguna Maitencillo and Quinterol; Concession period - 38 years