July 2021 - Project completed in April 2021; May 2019 - Construction commenced; October 2018 - Design works are currently underway; December 2017 - Budimex won contract worth PLN360.54mn (USD101mn) to design and build section; Budimex has 15 months to develop project documentation and obtain a ZRID decision