Theme Engineering Services Pvt. Ltd[Consultant/Project Management]{India},NKC Projects Private Limited[Construction]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2017
结束时间:
2022
项目说明:
February 2021 - Construction underway; October 2018 - 20% work is completed; November 2016 - NHAI has issued Letter of Award (LOA) for development of project; Project will be built under NHDP Phase IV-B and will have 2 major bridges, 5 minor bridges, 2 vehicular underpasses, one vehicular overpass and adequate road safety features; Project cost - INR13.72bn