Conecol[Sponsor]{Colombia},Episol[Sponsor]{Colombia},La Agencia Nacional de Infraestructura (ANI)[Sponsor]{Colombia}
项目状态:
Under construction
开始时间:
2018
结束时间:
2023
项目说明:
October 2021 - Construction underway; March 2021 - ANI plans to resume work on the Malla Vial del Meta road project in the second half of April; January 2021 - National Infrastructure Agency and Concesion Vial de los Llanos have signed agreement to reactivate and make viable the Malla Vial del Meta project; June 2020 - Construction work is being carried out with social distancing and other measures have been implemented to ensure safety of site personnel; April 2020 - Construction will resume after taking biosecurity measures to stop spread of Covid-19; June 2015 - ANI has awarded the development contract to Episol - Conecol consortium; The highway corridor will connect the Colombian cities of Villavicencio and Yopal, passing through the departments of Meta, Cundinamarca and Casanare; Project cost - COP2.6trn