National Highways Authority of India (NHAI)[Sponsor]{India},Sadbhav Engineering[Sponsor]{India}
项目状态:
Under construction
开始时间:
2019
结束时间:
2021
项目说明:
February 2021 - Construction underway; November 2020 - NHAI has invited bids for 700 m road from Waranga Junction (NH-161) to Mahagaon (NH-361) (existing Chainage 253.700) in Maharashtra on EPC mode; May 2019 - Construction progress rate is 42%; March 2017 - Sadbhav Infrastructure won construction contract; Project cost - INR16.69bn