Nepal Army[Construction]{Nepal},Asian Development Bank (ADB)[Feasibility]{Philippines},Government of Nepal[Sponsor]{Nepal}
项目状态:
Under construction
开始时间:
-
结束时间:
-
项目说明:
May 2020 - Construction underway; April 2020 - Nepal Army has issued a letter of intent to provide consultation services to design and supervise the construction of the Kathmandu-Nijgadh Expressway; August 2017 - Government handed over the 76.2 km section to Nepal Army; November 2016 - Government of Nepal cancelled the project with IL&FS because of the increment in cost to USD 1117mn from USD960mn in latest DPR; Project includes construction of 76.2 km Kathmandu - Nijgadh expressway and 18 km Nijgadh - Pathlaiya two-lane expressway converting into Four lane