Levantina Ingenieria y Construccion[Construction]{Spain},Serenissima Construction[Construction]{Italy},Municipality of Yerevan[Sponsor]{Armenia},Asian Development Bank (ADB)[Financier]{Philippines}
项目状态:
Under construction
开始时间:
2017
结束时间:
2021
项目说明:
November 2019 - Project to be completed by 2021; September 2019 - Construction has started again and bilateral memorandum for construction of the project was signed by Yerevan Municipality with Levantina Ingenieria y Construccion company; July 2018 - Contract with Serenissima Costruzioni was terminated in March 2017 due to its failure to implement construction works; March 2016 - Yerevan Municipality awarded contract to Serenissima Construzioni for the construction of project; Project includes construction of new 252 meter metal bridge crossing Hrazdan River and new 2.7 kilometer road and involves the construction of an overpass in the junction of Isakov and Babajanyan streets; Project is part of Western Yerevan Bypass