March 2020 - Construction commenced; January 2020 - Contract has already been awarded for Package I, II and VII while tender is under evaluation process for Package III, IV, V, VI, VIII and IX; August 2019 - February 2019 - MoRTH invited bids for Package IV, V, VI, VII, VIII and IX; February 2019 - MoRTH invited bids for Package I, II and III; Project is divided into 9 packages, Package I (117.5 km), Package II (129.4 km), Package III (104.3 km), Package IV (46 km), Package V (43 km), Package VI (40 km), Package VII (37.8 km), Package VIII (29.3 km), Package IX (37.1 km) |