国家和地区: |
Poland |
项目名称: |
S8 Expressway, Radziejowice - Paszkow Section, Masovian [id=7338] |
领域: |
Highway/Motorway |
项目类型: |
- |
项目性质: |
public |
项目经费 (USD Millions): |
- |
规模: |
21.50 |
规模单位: |
km |
参加单位: |
Strabag International[Construction]{Germany},European Investment Bank (EIB)[Financier]{Luxembourg},GDDKiA[Sponsor]{Poland},Intercor[Construction]{Poland},ZBM Inwestor Zastepczy SA[Consultant/Project Management]{Poland},MGGP SA[Consultant/Project Management]{Poland},European Union[Financier]{Belgium} |
项目状态: |
Completed |
开始时间: |
2016 |
结束时间: |
2019 |
项目说明: |
September 2019 - Radziejowice-Przeszkoda section was completed in July, while Przeszkoda-Paszkow section was completed in August of 2019; October 2014 - European Investment Bank (EIB) provides loan for the project; Project was carried out in 2 sections, 9.9km Radziejowice-Przeszkoda section and 11.5km Przeszkoda - Paszkow section; Project is part of S8 Expressway |
发布时间: |
2016 |