国家和地区: |
Indonesia |
项目名称: |
Ciawi - Sukabumi (Bocimi) Toll Road Project, West Java [id=9013] |
领域: |
Highway/Motorway |
项目类型: |
- |
项目性质: |
public |
项目经费 (USD Millions): |
594 |
规模: |
54 |
规模单位: |
km |
参加单位: |
Waskita Karya[Sponsor]{Indonesia},MNC Group[Sponsor]{Indonesia},PT Jasa Sarana[Sponsor]{Indonesia},PT Bukaka Teknik Ut[Sponsor]{Indonesia},PT Bakrieland Development[Construction]{Indonesia} |
项目状态: |
Under construction |
开始时间: |
2015 |
结束时间: |
- |
项目说明: |
November 2020 - Construction underway on section II while sections III and IV are under planning stage; December 2018 - Section I completed; February 2015 - Construction commenced on section I; Project includes 4 sections, 15.35 km Ciawi-Cigombong section, 11.9 km Cigombong-Cibadak, 13.7 km Cibadak - West Sukabumi and 13.05 km Sukabumi West - East Sukabumi; Toll road will be operated by PT Trans Jabar Tol, won by MNC Group, PT Jasa Sarana and PT Bukaka Teknik Utama; Project cost - IDR7.7trn |
发布时间: |
2015 |