项目说明: |
October 2020 - There is still no response to the request made to President Lopez Obrador two years ago, asking that the concession to build the highway be handed over to state administration; November 2019 - SICOM conducts study to demonstrate social profitability of project in order to carry tender and construction; October 2018 - Project will be under new state administration and the federation to start its construction through the management of resources; Project consists of design, construction, operation and maintenance of highway for 30 years; Highway to be built in 3 stretches, Silao - Juventino Rosos (18 km), Soledad Junction - El Xoconoxtle (30 km) and El Xoconoxtle - San Miguel de Allende (25 km); Project cost - MXN3.5bn |