Solomon Hochoy Highway Extension Project, Golconda - Point Fortin [id=19077]
国家和地区:
Trinidad & Tobago
项目名称:
Solomon Hochoy Highway Extension Project, Golconda - Point Fortin [id=19077]
领域:
Highway/Motorway
项目类型:
-
项目性质:
public
项目经费 (USD Millions):
1,155
规模:
47
规模单位:
km
参加单位:
Construtora OAS[Construction]{Brazil},Government of Trinidad and Tobago[Sponsor]{Trinidad & Tobago},National Infrastructure Development Company (Nidco)-Trinidad & Tobago[Sponsor]{Trinidad & Tobago},AECOM[Consultant/Project Management]{United States}
项目状态:
Under construction
开始时间:
2011
结束时间:
2020
项目说明:
October 2020 - Project under construction; December 2019 - Package 5 is 40% completed and has a cost of TTD280mn (USD41mn); November 2019 - Project is scheduled to be completed in December 2020; Construction commenced in 2011; Project cost - TTD7.5bn