Norwegian Public Roads Administration[Sponsor]{Norway},Veidekke Entreprenad[Construction]{Norway}
项目状态:
Under construction
开始时间:
2015
结束时间:
2022
项目说明:
February 2020 - Veidekke appeals the judgment on construction time; October 2018 - NOK1.1bn (USD133mn) has been added to the project in the state budget for 2019; July 2015 - NOK2.3bn (USD292mn) construction contract awarded to Veidekke; Construction commenced in September 2015 and the project is expected to open for traffic in 2022; Work includes the construction of the 1.5 km Skogafjell twin-bore tunnel, the 9.2 km Lyshorn twin-bore tunnel, a 1.7 km water tunnel and a 2 km four-lane open-air road