October 2020 - Further tenders for the project will start in Q32021; January 2020 - Design works underway and will last until the end of 2020; December 2019 - Design contract worth PLN7.6mn (USD2mn) has been signed with Mosty Gdansk for both the sections; Project will be implemented in 2 stages, Koszalin (end of the Koszalin and Sianow beltway) - Slawno (beginning of the Slawno beltway) and Slawno (beginning of the Slawno beltway) - Slupsk (beginning of the Slupsk beltway); Project is part of S6 Expressway which is expected to be completed in 2023