European Union[Financier]{Belgium},Germany Federal Ministry of Transport and Digital infrastructure (BMVI)[Sponsor]{Germany},Government of Germany[Sponsor]{Germany}
项目状态:
Under construction
开始时间:
2011
结束时间:
-
项目说明:
September 2020 - Colbitz-Tangerhutte (8.5 km) section opened to traffic, while construction underway on Dolle - Luderitz section; February 2018 - Approval granted for 18-km, EUR145mn (USD179mn) section between the future junctions Stendal-Mitte to Osterburg; December 2017 - The section between Grabow and Grob Warnow (11 km) has completed at a cost of EUR114mn (USD135mn); December 2015 - Federal government released Schwerin-Grabow section (16.2km) and Grob Warnow and Karstadt Section (11.3km) to traffic; EU invested EUR200mn (USD236mn) in the project; Project cost - EUR1.5bn