国家和地区: |
Poland |
项目名称: |
S7 Warszawa Lotnisko - Grojec Expressway, Masovian [id=36519] |
领域: |
Highway/Motorway |
项目类型: |
- |
项目性质: |
public |
项目经费 (USD Millions): |
411 |
规模: |
29.30 |
规模单位: |
km |
参加单位: |
European Union[Financier]{Belgium},Construcciones Rubau[Construction]{Spain},GDDKiA[Sponsor]{Poland},IDS-BUD S.A.[Construction]{Poland},Mota-Engil[Construction]{Portugal},Societe Anonyme Francaise d Etude de Gestion et d Entreprises (SAFEGE)[Consultant/Project Management]{France} |
项目状态: |
Under construction |
开始时间: |
2020 |
结束时间: |
2023 |
项目说明: |
October 2020 - IDS-Bud contract has been terminated while Tarczyn - Grojec Bypass section is on track for opening in 2021; February 2020 - Polaqua won contract for Warszawa Lotnisko - Lesznowola section, after GDDKiA decided to withdraw from the contract with Construcciones Rubau; May 2018 - Mota-Engil submitted application to obtain Road Investment Permit for its section; August 2017 - Construction contract awarded to Construcciones Rubau SA, IDS-BUD and Mota-Engil for Warszawa Lotnisko - Lesznowola section, Lesznowola - Tarczyn section and Tarczyn - Grojec bypass section respectively; Project to be carried out in 3 sections, 6.6km Warszawa Lotnisko - Lesznowola section, 14.8km Lesznowola - Tarczyn section and 7.9km Tarczyn - Grojec bypass; Project cost - PLN1.5bn |
发布时间: |
2020 |