Societe Anonyme Francaise d Etude de Gestion et d Entreprises (SAFEGE)[Consultant/Project Management]{France},GDDKiA[Sponsor]{Poland},POLAQUA Sp. z o. o.[Construction]{Poland},European Union[Financier]{Belgium}
项目状态:
Under construction
开始时间:
2020
结束时间:
2022
项目说明:
October 2020 - Construction underway; February 2020 - Polaqua has been selected after GDDKiA decided to withdraw from the contract with Construcciones Rubau; June 2018 - Construcciones Rubau SA submitted application to obtain Road Investment Permit (ZRID) from Mazowsze (Masovian Voivodeship); August 2017 - Construction contract worth PLN221mn (USD61mn) awarded to Construcciones Rubau SA for the section; Design and construction expected to be completed 34 months excluding winter months from December to March; Project is part of PLN1.5bn (USD411mn), 29.3km Warszawa Lotnisko - Grojec Section of S7 Expressway