Jiangsu Provincial Department of Transportation[Sponsor]{China}
项目状态:
Under construction
开始时间:
2018
结束时间:
2020
项目说明:
March 2020 - Construction underway while project completed the first integral hoisting construction of the cap beam steel bar; August 2019 - First piece of the bridge pier successfully completed; December 2018 - Construction commenced; Jiangsu section has a total of 14 mainline bridges, 8 ramp bridges, 4 crossed bridges and 988 piers; Project is a part of Liyang - Ningde Expressway