摘要: |
Immersed in the grand beauty of the Rocky Mountains, this project combines mountain charm and luxurious living in a highly sought-after vacation destination. This project added five additional mixed-use structures to service the current residents and the ski base area.
Erected at a challenging mountain jobsite, the buildings had strict seismic design requirements and had to be delivered in tight time frames despite unpredictable winter weather. The designer chose a total-precast concrete solution using emulative design techniques to meet all of these challenges. The emulative design cut 24 months from the original cast-in-place construction timeline, while netting the owner extensive cost savings. The design also met all seismic requirements and allowed the architect to incorporate higher ceilings without making the building taller. |