摘要: |
Scheduled maintenance and repair work at Lock 24, at Mississippi River Mile 273.4, near Clarksville, Mo., has been underway since the lock dewater-ing was completed January 23. Upper bulkheads were set January 14-15; lower bulkheads were set January 16-17; pumps were set January 20, and dewa-tering began January 21. Crane work and dewatering of the chamber was performed under contract by Massman Constructors. Repairs to miter gates as well as smaller repairs to bubbler piping, debris shields and floating mooring bitts as well as inspections were performed by Corps skilled labor crews and engineers. |