国家和地区: |
Zambia |
项目名称: |
Kenneth Kaunda International Airport Upgrade Project, Lusaka |
领域: |
Airport Expansion |
项目类型: |
ATC Tower,Apron,Baggage Handling System,New Terminal,Taxiway |
项目性质: |
Public |
项目经费 (USD Millions): |
360 |
规模: |
4 |
规模单位: |
million passengers per year |
参加单位: |
China Jiangxi Corporation for International Economic and Technical Cooperation[Construction]{China},Government of Zambia[Sponsor]{Zambia},National Airports Corporation-Zambia[Operator]{Zambia},Exim Bank of China[Financier]{China},China Airport Construction Group Corporation-CAAC[Design/Architect]{China} |
项目状态: |
Under construction |
开始时间: |
2015 |
结束时间: |
- |
项目说明: |
January 2022 - Construction underway; August 2021 - Second terminal building commissioned; February 2021 - Construction progress is 87%; October 2019 - Work has been delayed as EXIM Bank of China has halted the funding; October 2015 - Construction commenced in June 2015; [B&R] |
发布时间: |
2015 |