项目说明: |
November 2021 - Project under planning stage; January 2021 - Ministry of Transport will study the plan to relocate the station when there will be an interested investor; May 2020 - Ministry of Transport proposed that PM approved to the people's committee of Ho Chi Minh City as agency to prepare the pre-feasibility study report; November 2019 - Project is facing financial shortage; April 2017 - Stage I involves construction of 18.26 km of new rail track and improvement of 7 km of existing, which involves cost of VND3451bn (USD150mn), 4 options to fund the Stage I - BT, BTL, BOT or ODA loans; Project cost - VND12trn |