Indian Railways[Operator]{India},Hindustan Construction Company (HCC)[Construction]{India},Ircon International[Construction]{India}
项目状态:
Under construction
开始时间:
2019
结束时间:
-
项目说明:
May 2021 - IRCON invites bids for supply of Electronic Interlocking system for the project; December 2020 - Project is under construction; June 2019 - IRCON invites bids for electro mechanical (E&M) system; March 2019 - Construction underway; March 2014 - IRCON re - invited bids for construction of a tunnel at Arpinchala Yard in Jammu & Kashmir; January 2014 - Hindustan Construction Company (HCC) awarded contract for the construction of a tunnel and two bridges of the section; Project is a part of the Udhampur-Srinagar-Baramulla new BG railway line project; Project is being carried out in 2 sections, 17.68 km Qazigund - Banihal Section which was completed in December 2012 and 39 km Dharam -Banihal Section which is under construction