Tianjin Rail Transit Group Co Ltd[Sponsor]{China},China Railway Shanghai Engineering Bureau[Construction]{China}
项目状态:
Under construction
开始时间:
2013
结束时间:
2025
项目说明:
September 2021 - The 16 stations in the northern section have been fully started; August 2021 - The southern section officially entered the stage of no-load trial operation; January 2021 - Completion is planned for this year for southern section; March 2020 - Construction started on Northern section of the line; March 2019 - Bids invited for 114 cars to be operated as 19 six-car trains for southern section; Project will be built in two sections, 23.9 km northern section from Xiaojie Station - Southeast Point Station and 19.4 km southern section from Southeast point Station - Xinxingcun Station