China State Construction Engineering Corporation (CSCEC)[Construction]{China},Tianjin Rail Transit Group Co Ltd[Sponsor]{China}
项目状态:
Completed
开始时间:
2016
结束时间:
2021
项目说明:
October 2021 - The entire line has entered the no-load trial operation stage; March 2021 - Tunnelling work completed on Phase II; July 2020 - Phase II construction have been started; December 2016 - Northern section of Phase I officially put into operation; Project is being built in 2 phases, 45 km Phase I from Water Park East Road Station to Meilin Road Station and 14.34 km Phase II from Merlin Road Station to Xianshui West Railway Station