Wardha (Sewagram)- Ballarshah Third Railway Line, Maharashtra
国家和地区:
India
项目名称:
Wardha (Sewagram)- Ballarshah Third Railway Line, Maharashtra
领域:
Mainline
项目类型:
Upgrade/Maintenance
项目性质:
Public
项目经费 (USD Millions):
211
规模:
132
规模单位:
km
参加单位:
Indian Railways[Sponsor]{India},Abhi Engineering Corporation Pvt Ltd[Construction]{India}
项目状态:
Under construction
开始时间:
2017
结束时间:
2023
项目说明:
February 2021 - Project received funding in the budget; December 2020 - Work 29% completed; February 2020 - INR1.6bn (USD22mn) allocated for project in budget; September 2019 - Sewagram-Sonegaon (13.14 km) section opened; May 2017 - Foundation stone laid; February 2016 - Cabinet Committee on Economic Affairs (CCEA) approved the project, project is expected to take more than 5 years to complete; Project Value - INR14.43bn