国家和地区: |
India |
项目名称: |
Alappuzha Bypass Project, NH-47 (new NH.66), Kerala |
领域: |
Road |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
54 |
规模: |
6.8 |
规模单位: |
km |
参加单位: |
RDS Project Ltd[Construction]{India},Government of India[Sponsor]{India},Kerala State Government[Sponsor]{India},National Highways Authority of India (NHAI)[Sponsor]{India},Cheriyan Varkey and Sons Ltd[Construction]{India} |
项目状态: |
Completed |
开始时间: |
- |
结束时间: |
2021 |
项目说明: |
January 2021 - Bypass opened for traffic; November 2020 - Project to be opened for traffic by December end; Project consists of two rail overbridges (RoB) at Malikamukku and Kuthirapanthy; Road will have two major junctions at Kommady and Kalarcode, four minor junctions and 14 culverts; Work on the Alappuzha Bypass began in 1972, while construction of the bridge began several times and then stalled; Project Value - INR3.484bn |