Cherthala-Oachira Section (NH-47) Four Laning Project, Kerala
国家和地区: India
项目名称: Cherthala-Oachira Section (NH-47) Four Laning Project, Kerala
领域: Highway/Motorway
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): -
规模: 86
规模单位: km
参加单位: National Highways Authority of India (NHAI)[Sponsor]{India},Soma Enterprises Limited[Sponsor]{India},Isolux Corsan[Sponsor]{Spain},SMEC[Consultant/Project Management]{Australia},Japan Bank for International Cooperation[Financier]{Japan},Asian Development Bank (ADB)[Financier]{Philippines},World Bank[Financier]{United States}
项目状态: Under construction
开始时间: 2020
结束时间: -
项目说明: January 2021 - Alappuzha bypass completed; February 2018 - Works to widen the corridor will begin in June and expected to be done by December 2020; March 2017 - Detailed project report and bid document reach NHAI for approval; July 2016 - Land acquisition to begin soon for the project
发布时间: 2020