India Public Works Department (PWD)[Sponsor]{India},Larsen & Toubro (L&T)[Construction]{India}
项目状态:
Under construction
开始时间:
2015
结束时间:
2021
项目说明:
June 2021 - Contractor has filed a case of arbitration against Delhi Government over the losses caused by land acquisition issue under Phase-III; September 2019 - PWD has scrapped the eagerly awaited fourth phase, instead proposed two alternatives; July 2018 - Phase II completed; February 2017 - Feasibility study started for phase IV; March 2015 - Construction contract awarded to L&T for phase III; 4 km stretch under phase I of the Barapullah elevated road, connecting Sarai Kale Khan and JLN Stadium started in September 2008 with ground breaking and has been operational since 2010