Barapullah Elevated Corridor - Phase III, Delhi
国家和地区: India
项目名称: Barapullah Elevated Corridor - Phase III, Delhi
领域: Road
项目类型: -
项目性质: Public
项目经费 (USD Millions): 164
规模: 9.5
规模单位: km
参加单位: Larsen & Toubro (L&T)[Construction]{India},India Public Works Department (PWD)[Sponsor]{India}
项目状态: Under construction
开始时间: 2015
结束时间: 2021
项目说明: June 2021 - Contractor has filed a case of arbitration against Delhi Government over the losses caused by land acquisition issue; September 2019 - 70% construction work has been completed; March 2015 - Construction contract awarded to L&T; December 2014 - Foundation stone laid for construction; Phase-III will connect Sarai Kale Khan in south Delhi to Mayur Vihar-I in east Delhi; Project is part of Barapullah Elevated Corridor; Project cost - INR11.42bn