Asian Infrastructure Investment Bank[Financier]{China},Maharashtra State Government[Sponsor]{India},Mumbai Rail Vikas Corporation (MRVC)[Sponsor]{India},Aarvee Associates[Consultant/Project Management]{India},Egis Rail[Feasibility]{United Kingdom}
项目状态:
Under construction
开始时间:
2020
结束时间:
-
项目说明:
February 2021 - CIDCO transfers the necessary land to MRVC for the project; August 2020 - Mumbai Rail Vikas Corporation (MRVC) along with the Maharashtra government signed a loan agreement of INR3.5bn (USD471mn) with the Asian Infrastructure Investment Bank (AIIB) for railway projects under the MUTP III; July 2020 - Construction is underway on a new stop at Digha; January 2020 - Line may have to be redesigned again due conflict of interest between Central Railway (CR) and Mumbai Rail Vikas Corporation; December 2016 - Union Cabinet approved project under INR109.47bn (USD1.6bn) Mumbai Urban Transport Project Phase-III (MUTP III); Project cost - INR4.76bn; [B&R]