IL & FS Engineering and Construction[Construction]{India},Ministry of Road Transport & Highways[Sponsor]{India},Translink[Consultant/Project Management]{Australia}
项目状态:
In tender/Tender launched
开始时间:
2018
结束时间:
-
项目说明:
February 2021 - Construction work 35% completed; March 2020 - Invited bids for balance work of construction; July 2019 - Construction on 3.11 km has been completed; January 2017 - IL&FS has received a Letter of Acceptance (LoA) for a road contract; Project involves widening of two/four lane with paved shoulders from km 54.37 to km 101.400 (Bidar to Humnabad) Section of NH-50; Project Value - INR3.67bn