Sinnar - Nashik Section Four Laning, NH-50, Maharashtra
国家和地区: India
项目名称: Sinnar - Nashik Section Four Laning, NH-50, Maharashtra
领域: Highway/Motorway
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 51
规模: 22.5
规模单位: km
参加单位: National Highways Authority of India (NHAI)[Sponsor]{India},Chetak Enterprises Ltd[Consultant/Project Management]{India},Maharashtra Public Works Department[Sponsor]{India}
项目状态: Under construction
开始时间: 2015
结束时间: 2021
项目说明: November 2020 - Construction underway, work will be completed by March 2021; May 2015 - Construction commenced; August 2013 - Government of India and MORTH has invited bids for the project on Design-Build-Finance-Operate-Transfer (DBFOT) Toll basis; Project includes development of Sinnar to Nashik section of NH-50 from 177.00 km to 201.35 km of Pune -Nashik road, widening of existing 7 meter wide road to 4-lane in length of 15.80 km and construction of new Sinnar bypass four lane road in length of 9.51 km; Project Value - INR3.13bn