National Highways Authority of India (NHAI)[Sponsor]{India},Eagle Infra India Ltd[Construction]{India}
项目状态:
Under construction
开始时间:
2016
结束时间:
2021
项目说明:
August 2021 - Construction underway, to be completed by October 2021; April 2020 - Construction halted; March 2016 - Foundation stone laid; Project includes construction of four lane (Partially Access Controlled) Laddowal bypass (linking NH-95 with NH-1 via Laddowal Seed Farm) on Hybrid Annuity Mode (HAM) taking off from NH-95 (under execution as part of Southern bypass) running along Sidhwan canal and passes via Laddowal Seed Farm at Ludhiana of NH-1; Project cost - INR3.7bn