New 4-Laned MG Setu Parallel Bridge (NH-19), Bihar
国家和地区:
India
项目名称:
New 4-Laned MG Setu Parallel Bridge (NH-19), Bihar
领域:
Road
项目类型:
Bridge
项目性质:
Public
项目经费 (USD Millions):
245
规模:
14.5
规模单位:
km
参加单位:
Government of India[Sponsor]{India}
项目状态:
Under construction
开始时间:
2021
结束时间:
2024
项目说明:
July 2021 - Foundation work is being done; June 2020 - Technical evaluation is being done and the companies which qualify will go for financial bid; August 2019 - Tender has been floated for construction of four-lane bridge; December 2018 - Government approved the project; Bridge will be build parallel to existing Mahatma Gandhi Setu on River Ganga; Project cost - INR17.94bn