New 4-Laned MG Setu Parallel Bridge (NH-19), Bihar
国家和地区: India
项目名称: New 4-Laned MG Setu Parallel Bridge (NH-19), Bihar
领域: Road
项目类型: Bridge
项目性质: Public
项目经费 (USD Millions): 245
规模: 14.5
规模单位: km
参加单位: Government of India[Sponsor]{India}
项目状态: Under construction
开始时间: 2021
结束时间: 2024
项目说明: July 2021 - Foundation work is being done; June 2020 - Technical evaluation is being done and the companies which qualify will go for financial bid; August 2019 - Tender has been floated for construction of four-lane bridge; December 2018 - Government approved the project; Bridge will be build parallel to existing Mahatma Gandhi Setu on River Ganga; Project cost - INR17.94bn
发布时间: 2021