Oriental Structural Engineers (OSE)[Construction]{India},HG Infrastructure[Construction]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2021
项目说明:
April 2021 - Construction underway; October 2020 - NHAI has allowed partial resumption of work on the project on which the work was stopped after the collapse of a concrete slab of an elevated corridor in August; February 2020 - 40% work has been completed in the second package while around 15% has been done in the first package; October 2018 - Construction commenced; Project to be carried out in 2 packages, Package I includes 9 km Rajiv Chowk - Badshahpur while Package II includes 12 km Badshapur - Sohna; Project Value - INR13bn