Dilip Buildcon Ltd[Operator]{India},State Bank of India[Financier]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
August 2021 - Six bypasses along the highway under construction; October 2019 - Funds allotted for the highway were diverted to flood rehabilitation; March 2018 - National Highways Authority of India (NHAI) has issued LOA for development of the project to Dilip Buildcon Limited on Hybrid Annuity Mode; Project is taken up under Bharatmala Pariyojana Phase I part of 117.3 km, Bangalore - Mysore Highway (NH-275) Six-laning project costing INR80.66bn (USD1.1bn); Project cost - INR30bn