项目说明: |
September 2021 - Construction underway; September 2020 - 7% was completed by July 2020 and 30% progress is expected by August 2022; April 2020 - Construction will resume after taking biosecurity measures to stop spread of Covid-19; February 2020 - Macquarie has reached an agreement to acquire 100% stake in the concession, while CSS Constructores, subsidiary of grupo Solarte will remain as the construction contractor; July 2019 - Project has received an environmental license; April 2016 - CSS Constructores signed concession contract; Project involves the development of 13.5km of new road, improvement of 51km and rehabilitation 68.6km of road linking Bucaramanga with the city of Pamplona, which includes the Bucaramanga bypass and the Floridablanca bypass; Project cost - COP1.8trn |