国家和地区: | Colombia |
项目名称: | Pamplona - Cucuta Highway Rehabilitation Project |
领域: | Highway/Motorway |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 480 |
规模: | 122.4 |
规模单位: | km |
参加单位: | Industrial and Commercial Bank of China (ICBC)[Financier]{China},Deutsche Bank[Financier]{Germany},FDN (Financiera Nacional de Desarrollo)[Financier]{Colombia},JPMorgan Chase[Financier]{United States},Sacyr Vallehermoso[Sponsor]{Spain},La Agencia Nacional de Infraestructura (ANI)[Sponsor]{Colombia},Societe Generale[Financier]{France},MUFG Bank Ltd[Financier]{Japan},MetLife[Financier]{United States},Instituto de Credito Oficial[Financier]{Spain},Bank of China[Financier]{China} |
项目状态: | Under construction |
开始时间: | 2019 |
结束时间: | - |
项目说明: | December 2021 - 52% work completed; June 2021 - Construction underway on Pamplona tunnel; December 2020 - 62.6 km rehabilitation completed; March 2020 - Sacyr secured financing of EUR474mn (USD524.5mn); July 2019 - Construction has started on a tunnel, as part of the project; April 2017 - ANI awarded construction contract to Sacyr; Project includes new road construction on 50.2km and rehabilitation on 72.2 km of the existing road; Project cost - COP1.87trn |
发布时间: | 2019 |