National Highways & Infrastructure Development (NHIDCL)[Sponsor]{India},Tarmat Limited[Construction]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2021
项目说明:
August 2021 - Tarmat Limited Company was put in negative list for delay in construction work; May 2020 - Construction resumed after it was suspended due to nationwide lockdown amid COVID-19; March 2018 - Ministry of Road Transport & Highways (MoRTH) approved rehabilitation and upgrade of Jammu - Akhnoor section of NH-144A; Section will be upgraded to four lanes with paved shoulders under EPC mode; Project cost - INR9.17bn